Roadmap
Début Projets
about 13 months late (01/31/2020)
76%
20 issues (2 closed — 18 open)
Revue de début de projet
about 12 months late (03/11/2020)
0%
Polytech Ge Sous Traitance - Première Itération 2020
about 5 months late (10/14/2020)
35%
162 issues (34 closed — 128 open)
Polytech Ge Sous Traitance - Deuxième Itération 2020
about 4 months late (11/06/2020)
54%
110 issues (45 closed — 65 open)
Polytech Ge Sous Traitance - Troisième Itération 2020
about 3 months late (11/23/2020)
60%
47 issues (21 closed — 26 open)
Revue de fin de projets
about 3 months late (12/16/2020)
100%
Polytech Ge Sous Traitance - Quatrième Itération 2020
60 days late (12/31/2020)
63%